On May 30, 2012 a regular operational meeting involving experts of “NIBULON” and managers of contractors was held at the construction site of “Pereyaslavs`ka” branch. There is only a month left to complete the construction, thus contractors are currently speeding up the work pace in order not to bring the customer and complete works on time. Moreover, the terminal should be ready for the reception of a new harvest. Here is the progress schedule. PE “Transvit” has completed installation of the last foundations of granaries. PJSC “Astarta” completes assembly of truck tipper ramps and its lower conveyors by June 6. Ltd. “Poltavaspetsmontazh” completes installation of bridges, gallery support by June 6. Ltd. “Oll-Ingyniring” by June 6 will have completed work in the weighting station, including landscaping around, finishing in the elevator station; by June 10 works on administrative and laboratory building refinishing will have been completed. Ltd. “Ukrbauer” will have fulfilled the arrangement of an access road with a total length of 3.5 thousand sq m. by June 6. PE “Crystal 2007″completes finishing works in industrial workshops by June 10. Ltd. “Construction Company” will have to complete installation of elevator tower metal structures with its coating by June 10. Ltd. “Integral” completes assembly of the first three granaries by June 10. PE “Scherbina” will have installed heating, sanitation, ventilation systems in residential areas by June 10. Ltd. “Yuzhelektromontazh” will have provided illuminating effect at the site by 10 June. PE “Stal’budinvest” will have installed technical equipment in the elevator tower by June 12. Ltd. “TCS” will have to complete upper galleries assembly by June 14. Ltd. “Gidrotehnologiyi” will have to build a berth foundation and install a berthing wall by June 14. PE “Styl’ Teplo Comfort” will have installed household sewage system by June 14. Ltd. “Zahidshlyahbud-Beton” will have to complete concrete works on improvement by June 15. Ltd. “BOSS” will have energized at the site by June 15. There will be a solemn commissioning of the terminal in late June, as noted earlier. The predefined scheduled time will not be postponed! We will inform you about the exact date of the event in advance. Please find attached the photo report.