There is a photo report about status of St.Mykolai floating crane construction of NB 603 manufacturing order.
***
At present there have been approved erection joint of unit No20, unit No90 (navigation house) and crane boom support. Unit No90 has been cleaned and the priming coat was put. Painting of crane boom support is in the final stage.
Fitter’s woks on assembly of starboard section No10 to unit No20 have been completed. There have also been completed assembly and welding works to install crane support surface on unit No70. The latter has been approved and is being painted now.
The shipyard specialists finish assembly and welding works on port section No10, port section No30, starboard section No30, port section No40, and on unit No50 (aft superstructure).
The shipyard workers have concreted dry ballast tanks. There has been started installation of mooring equipment (bollards, hawses) on the main deck and equipment assembly in the engine room.