At present the total readiness of St.Mykolai floating crane is 17%. The workers of Santierul Naval Constanta shipyard work in two shifts, above 100 employees are engaged in carrying out the shipbuilding order. Thus, the Romanian party confirms its reputation of a reliable partner assuring vessel’s delivery to NIBULON within the contract limit. We would remind you that the construction completion is scheduled for March 23, 2013.
The next photo report about status of the floating crane construction is for your attention.
Subassembly
Manufacturing of assemblies of the unit No80 (forward deckhouse) has been completed. Now production of assemblies of the units No30 (its readiness comprises 45%) and No60 (forward deckhouse – 50%) is being continued.
Fabrication
Assembly and welding works to enlarge port section No20 are being finished, its outfitting with pipe lines is being conducted, installation of foundations and welded outfitting is being performed. The section is being prepared for approval.
Installation work on the unit No70 (crane pillar) is being completed, soon there will be started welding.
The shipbuilders have assembled the unit No80, there are performed assembly and welding works to install welded outfitting.
Readiness of manufacturing of sections and units comprises: starboard section No10 – 30%; port section No10 – 38%; port section No20 – 85%; starboard section No40 – 55%; port section No40 – 42%; unit No70 – 50%; unit No80 – 60%.
Manufacture and assembly of electric locksmith outfitting are being continued.