At shipbuilding yard“Wadan Yards Okean”two new non-self-propelled vesselsof NIBULON are waiting for the launching– they are the last of 16 vessels, contracts were signed on the 6th of March, 2009. Those two barges were built very quickly, despite all the severe weather conditions: snowstorms, low temperature etc.
Construction of the next eight vessels is being continued steadily in the shops of the yard, contracts were signed on the 3rd of December, 2009.
Specialists of NIBULON, who paid a friendly visit to the yard, brought the good news. We provide you with detailed information of the status of NIBULON’s fleet construction.
The construction of vessels on the contracts from the 3rd of December, 2009:
Orders №№ 175, 176: manufacturing of sections and assembly units is being finished, keel-laying in the graving dock is started.
Orders №№ 177-178: metal cutting is being performed; manufacturing of sections and assembly units is in the process.
Orders №№ 179-182:intense cutting metal is being continued.