Order № 183: assembling of fendering protection is being continued on perimeter of the vessel. Workers of the yard made a mast, soon its installation will be started. Doors are installed in the navigation room, installation of portholes is started. Exterior walls of texas are being prepared for painting. Order № 184: significant progress was achieved in cabinet works by the workers of the yard during the last week. Bunker tanks, cooling premises, sea-valve boxes, dirt tanks, ballast tanks are already presented and checked on designability. Installing of deck equipment is started, foundations for main engines are already installed. Order № 185: hull works are continued at the workshop of the yard. Units № 2, 3, 4 are aggregated and welded together. Production of edge units is at the finish. Workers of the yard made lifting foundation for navigation room. Production of pipes for the ship systems and processing of transition slates is being continued. Order № 186: units № 20 and 30 are prepared for aggregation. Unit № 40 is next for aggregation. Manufacturing of fore and aftmost edge is at the finishing stage. Sections oftexas are aggregated by the workers of the yard in the workshop. Tapered pipes are prepared for mechanical processing.