The construction works at the site are coming to an end, workers are leaving the facility gradually… One of the last production meetings headed by Sergiy Besedin, the deputy general director for construction, was held at the site on July 10, 2012. There remain less than two weeks before completion of the construction works. At present the schedule of works are the following. “Transvit” company will have performed pre-operational testing of processing and transport equipment by July 12. “Kyivoblgaz” company will have completed installation of gas pipeline networks by July 12. “ALL-ENGINEERING” company will make concrete works in beautification of areas near dryers. “Solvi” company will have performed aspiration assembly by July 13. “Gidrotehnologiyi” company will have completed construction of berth foundation in full by July 13. “Zahidshlyahbud-beton” company will have completed concrete works in beautification of 3000 sq. meters. On July 24 with participation of Anatoliy Prusyazhnyuk, the Head of Kyiv regional state administration, there will be held festivities on the occasion of putting into operation of the transshipment terminal. Our partners and friends: representatives of local authorities, bankers, diplomats, ambassadors, management of contract organizations will be present at the event. For locals of Pereyaslav-Khmel’nyts’kyy district an opening of the transshipment terminal will be an unforgettable event. And prior to a solemn opening of the terminal there will be started an acceptance of grain and oil crops. You will be witnesses of all these, our dear readers, due to our next photo reports. And now the photo of the transshipment terminal is for your attention.